dcorrea • Oct 11, 2022

Last year I wrote an article about Forensic Delay Analysis on the back of COVID-19 claims.

Whilst the theory in the article remains correct, we are now in a position where we are retrospectively reviewing construction delays during COVID times (if it is true that COVID is no longer affecting projects…). As noted in such article, the main methodologies available to perform a retrospective analysis , according to the Society of Construction Law (2 nd Edition), are the following :

As further described in the Protocol, and explained in various of our articles and presentations, those 4 methodologies depend heavily on the documentation available, the time and budget the expert has, and the requirements for the particular claim.

For instance, both Windows Analysis continue to remain the favourite ones in large disputes, but when there is less information available and records were not kept to the expected level of quality, we see that the Retrospective Longest Path Analysis would become handy. It is indeed a method that some may consider more simplistic, but it does help the expert and the Parties to understand the retrospective as-built critical path of the project, and be able to understand how events unfolded from at least a higher level.

This would in turn facilitate a view on whether COVID related delays actually fell part of the longest critical path, or indeed were concurrent, or not even critical. I have read many articles of different law firms, at the time that COVID was happening, recommending contractors to keep good records for future claims:

See for example the article by Baker Mckenzie on January 2021.

One of the key elements listed there was to maintain the record of impacts . In particular, “ In the event a construction site is shut down due to a governmental order, owners should meet with their contractors to determine the status of their projects at the time of the shutdown and the work remaining. Moving forward, owners should request their contractors to submit detailed reports of impacts and real time itemization. Parties to construction contracts should regularly collect data regarding the circumstances affecting the work and their mitigating efforts. This data collection will allow the parties to accurately track impacts and anticipate delays and extra expenditures ”.

I completely agree with such ideal scenarios, but the question now is, was this done? Regrettably, in various of the cases we are involved at, the Parties did not record properly both the status of the project in different periods, or even less the impact that a shutdown would have on the completion of the project. This is because either the project was already in trouble before any COVID effects, or at the time these events occurred some key personnel were not present due to isolation, sickness, or company guidelines.

Pinsent Masons also recorded in August 2021 that ‘ Covid [was] to impact construction claims ‘until at least 2023’ .

The article highlights the well-known provision of “force majeure”, but most experts know that whilst delay incurred in a period of force majeure could be excusable (i.e. the contractor safe from Liquidated Damages), this is hardly compensable (i.e. the contractor paid for prolongation costs).

One key point that Pinsent Masons highlighted at that point was that in order to calculate the impact of disruption , the affected party would have to demonstrate what was the productivity that would have been achieved “but for” the effects and disruption caused by the pandemic (if any). In order to do this, the party would have to demonstrate the quality and validity of its records at the point when the effect would begin to occur. This again means that record keeping, as it should always be, is at the heart of delay claims on the back of COVID-19.

A study of the Construction Industry has shown, earlier this year, that 9 out of 10 large projects were behind schedule:

That means, of course, that only 10% of the projects ‘survived’ from the effects of the pandemic. The article certainly highlights issues with supply chains, as we discussed last year, and specifically highlights issues with the supply of structural steel as one of the most critical elements, given that there were shortages and increased prices (70% higher!).

What this all Means

The essence of this article is to highlight that in order to properly differentiate and demonstrate those delays incurred because of COVID related issues, the parties have to be able to segregate and organise all the project information as best as possible, including all available schedules, progress reports, site photographs, timesheets, relevant correspondence, invoices, and any other available piece of information that would help them, and their experts, to assess the delays and to assign responsibility. I would also recommend for these parties to locate key witnesses of fact, so that their relevant experience can be recorded properly, especially in the absence of substantial evidence.

Having said the above, the construction industry in Europe is having of course a second blast with the war in Ukraine. Whilst this is of course sadly still ongoing, the country will have to start re-building at some point and this would require a lot of resources of all kinds. It reminds me of a case I had in mid-2000’s in Dubai, when a major building complex was halted for a year because of Government regulations, and when the project resumed, they could not find the right personnel and relevant resources as the country’s construction industry was booming, so their expected productivity went to the floor. Similarly, I was involved in a complex construction dispute in Libya, that following the outing of Gaddafi in 2011, the project could not be properly completed due to the unsafe conditions in the country for various years and unavailability of vendors to complete key activities such as commissioning. That particular dispute lasted around 10 years, so clearly a lot of key personnel left the relevant companies, and therefore obtaining good contemporaneous information was difficult. Again, contemporaneous records should be saved like gold.

We expect that COVID-19 related claims will continue well beyond 2023, and this is basically because in some of the major engineering and construction disputes we get involved at, it takes at least some 3-4 years before we get appointed. At that point all these “recommendations” above would have been long forgotten by contractors, so we remain at their disposal to collate information NOW, and not in a few years’ time.

Daniel A. Correa

Managing Director

DAC Consulting Services Ltd

by Daniel Correa 15 Apr, 2024
In the intricate and highly specialized realm of engineering and construction, disputes and claims are not just common—they are expected.
by Daniel Correa 03 Apr, 2024
DAC Consulting Services is proud to have attended and sponsored this impressive event, which confirms our investment in the Middle East and North Africa region.
by Daniel Correa 19 Mar, 2024
Reflections on the SCCA24 Conference: Shaping the Future of Arbitration in Riyadh
by Marcus Elliott 30 Dec, 2023
Merry Xmas to everyone! May this season fill you all with hope, happiness,  kindness, wisdom, and faith.
by Marcus Elliott 21 Dec, 2023
WORLD CLASS FORENSIC & TECHNICAL CONSULTANTS
by Marcus Elliott 24 Nov, 2023
Over the past year, expert witnesses have appeared in the legal press following criticism in the courts. So for this year’s Sir Michael Davies lecture, we invited The Honourable Mr Justice Williams, High Court judge and chair of The Family Justice Council Subcommittee on Experts, to share his views on such criticism. In his enlightening keynote speech – which you can listen to in full here – Mr Justice Williams explored an array of issues relating to the criticism of experts. Distinguishing between constructive criticism, destructive criticism and disagreement, he guided the audience through criticism in the context of the work he’s doing with the Family Justice Council, along with recent judicial commentary on expert evidence. He also made excellent suggestions around what to do if you find yourself being criticised as an expert, as well as how to avoid finding yourself in that situation in the first place. We’ve summarised some of the key takeaways below. Constructive vs destructive Criticism isn’t all bad, Mr Justice Williams noted. Constructive feedback to an expert can help improve the way that other experts approach courts in the future — and that can only be a good thing. But judges are aware of the importance of protecting experts from unfair, destructive criticism. “Criticism in a judgement can have adverse consequences in terms of [experts’] reputation, referrals to professional bodies, and on business”, Mr Justice Williams noted. All experts should remember, though, that disagreement from a judge is not necessarily criticism. “Don’t be too sensitive!”, he reminded the audience. Common criticism A lack of preparation, failure to abide by court directions, going beyond remit or expertise, and poor presentation on paper and on screen are all areas where experts commonly face criticism. The possibility of being criticised in court was highlighted as a barrier for attracting experts – though it’s important to note that it was by no means the biggest barrier. “As the judiciary, it’s entirely within our hands to manage criticism of experts”, Mr Justice Williams acknowledged. Efforts to change the way that criticism is managed have been made in the family law arena, with the establishment of a working group, the Family Justice Council Sub-Committee on Experts. The good, the bad and the ugly Mr Justice Williams highlighted three areas likely to put you in a positive light in the eyes of a High Court judge: the ability to express complex concepts in accessible language; objectivity and staying within the bounds of your expertise; and, of course, sticking to the facts. At the opposite end of the spectrum, being unprepared; not abiding by court directions; and going beyond your remit or expertise are all traits that are likely to attract criticism from a judge. As for the ugly – make sure that your presentation on paper and on screen is up to scratch! How to avoid destructive criticism No Expert Witnesses want to attract destructive criticism. To help avoid it altogether, Mr Justice Williams’ top tips included: don’t take on too much; comply with timetables; and communicate any difficulties. “Can’t complete the work in the time you thought you would? Let us know and we can do something about it”, Mr Justice Williams pointed out. Importantly, he said, remember the fundamentals of being an expert: comply with your subject matter expertise and with procedural codes. Managing criticism “If you’re being criticised in court, the best position to take is to remain as objective as possible and try to give considered answers”, is Mr Justice Williams’ advice for managing criticism. “If you need it, ask for time to respond.” If you’re facing criticism, seek support: the Expert Witness Institute fulfils that mentoring and support role. “Destructive criticism can also be valuable as a learning process in itself”, Mr Justice Williams reminded us. “It illustrates to the broader community that bad practice is a part of everyone learning.” The happy judge Judges are very busy people – that’s partly why the presentation of expert reports, with an executive summary of four pages, is so important. “If you’re clear in your conclusion with clear and practical advice with a range of opinions, where relevant, the judge is going to be on your side to start with”, Mr Justice Williams said. “If you’ve got a happy judge, even if you’re robustly cross examined, having the judge on side is something to value.” The audience were reminded that criticism is not all bad. In fact, it is rare, and it is relatively easily avoided. Ultimately: “The judiciary want experts to continue being experts, we want you to enjoy being an expert, and we don’t like criticising (although we all like a robust exchange of views).” Listen to the full lecture Access the recording of the Sir Michael Davies Lecture 2023 – you’ll also get a CPD Certificate worth ¾ hour.
by Marcus Elliott 13 Oct, 2023
WORLD CLASS FORENSIC & TECHNICAL CONSULTANTS
by Marcus Elliott 20 Sept, 2023
¿Qué repercusiones tendrá en el sector asegurador? Empecemos señalando que, hasta el momento, en México, específicamente en la Ciudad de México, no había un lineamiento claro sobre cómo se deben evaluar las estructuras y, posteriormente, cómo deberían ser rehabilitadas. La falta de una norma específica no implica que, hasta ahora, este proceso se hiciera mal, sino que la variedad de criterios para considerar que los daños en un edificio son sujetos de un proyecto de rehabilitación es muy grande y depende enteramente de la experiencia del ingeniero a cargo. Para dar un poco de contexto, la CDMX tiene varias Normas Técnicas Complementarias (NTC) que, como su nombre lo dice, complementan de forma técnica al Reglamento de Construcciones. Dichas NTC, proporcionan los requisitos y criterios para el diseño de los elementos estructurales de un edificio, por ejemplo, una columna de concreto, un contraviento de acero o una pila en la cimentación. Durante agosto y septiembre, el Gobierno de la Ciudad de México realizó un ciclo de conferencias en el Colegio de Ingenieros Civiles de México, para presentar las actualizaciones a las NTC publicadas en 2017 y para presentar una norma nueva que es muy necesaria y que, desde mi punto de vista, tendrá un gran impacto en la forma en la que el sector asegurador revisa las propiedades ya sea para evaluar el riesgo o para cuantificar los daños. Lo que pretende la nueva norma es proveer la metodología para evaluar una estructura y los requisitos mínimos para su rehabilitación, en caso de ser necesaria. Aunque esta NTC es aplicable a todos los EDIFICIOS (no aplica a otras estructuras como puentes o tanques de almacenamiento) en la CDMX, independientemente de si tienen daño visible o no, en este artículo me enfocaré únicamente en lo que ocurrirá con los que sí tienen daños, es decir, los que se verán involucrados en una reclamación de seguros. La NTC está dividida en 13 capítulos y 2 apéndices, los cuales, a su vez, hacen referencia a las NTC aplicables del material estructural a rehabilitar. En los siguientes párrafos abordaré de forma general el objetivo de cada uno y sus implicaciones más relevante.
by Marcus Elliott 11 Sept, 2023
We're proud to announce that our Managing Director, Mr Daniel Correa is a guest speaker at this year's Istanbul Arbitration Week 2023
by Marcus Elliott 29 Aug, 2023
Carbon Capture: The Real Energy Transition. What is carbon capture, and why should we focus on that as a climate solution rather than end our reliance on fossil fuels right now?
More posts
Share by: